The important file in making a PERT is__________________?


aan event can’t be accomplished until activities leading to it are completed

✖


bno activity from any event can be started from preceding event till it is completed

✖


clength of arrow has nothing to do with time

✖


dall of the above

✓


View Answer all of the above

Pessimistic time is___________________?


athe maximum time which an activity might require

✓


bthe average time required for a job

✖


cthe most probable time considering all conditions

✖


dthe minimum time in which an activity can possibly be accomplished

✖



In a PERT chart___________________?


aall activities should be numbered

✓


bonly important activities should be numbered

✖


conly critical activities are numbered

✖


donly selected activities are numbered

✖



In PERT analysis, critical path is obtained by joining events having___________________?


a+ve slack

✖


b-ve slack

✖


czero sldck

✓


ddummy activities

✖


View Answer zero sldck

Positive slack on a PERT indicates that project is________________?


aahead of schedule

✓


bbeyond schedule

✖


cas per schedule

✖


don critical path

✖


View Answer ahead of schedule

An event is indicated on the network by_________________?


aa straight line

✖


ba number enclosed in a circle or a square

✓


ca straight line with circles at the ends

✖


da dotted line

✖



Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?


alatest start time of succeeding event -earliest finish time of preceding event activity time

✖


blatest start time of the event – earliest start time of the event

✖


clatest finish time of event – earliest finish time of the event

✖


danyone of the above

✓


View Answer anyone of the above

Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?


aconsumes time, but no resources

✖


bconsumes resources but no time

✖


cconsumes neither time nor resources

✓


dis a dangling event

✖



Slack of various events on the critical path in PERT/CPM chart___________________?


aincreases continuously

✖


bdecreases continuously

✖


cremains constant

✓


dmay increase or decrease depending on various factors

✖


View Answer remains constant

Descripancies of bar chart techniques are________________?


aDescripancies of bar chart techniques are________________?

✖


bconsequential effects of lack in one activity on the finish date

✖


cfree time available for an activity can’t be predicted

✖


dall of the above

✓


View Answer all of the above

Goto Page No.

Page 62 of 190

Alphabetical MCQs Categories
—

Here below You find all kind of categories of MCQs in alphabetical order.


"Comprehensive Collection of MCQs: Alphabetically Organized by Subject"
—

"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"


BolPakistan

bolpakistan.com.pk includes Job Mcqs and Pak Mcqs is the Top Largest Mcqs Forum in World, in which you can read Mcqs of All Subjects, PPSC test preparation, FPSC, NTS and PPSC PAST PAPERS, PPSC PAST MCQS. A Collection of Repeated MCQs for JOBs seekers.

Copyright © 2024, Designed & Developed by BolPakistan