The critical path of a network represents_______________________?


athe minimum time required for completion of project


bthe maximum time required for completion of project


cmaximum cost required for completion of project


dminimum cost required for completion of project



Critical path moves along the activities having total float of_____________________?


apositive value


bnegative value


czero value


dsame value


View Answer zero value

Pick up the correct statement about relationship between various floats______________________?


afree float = total float


bindependent float = total float


cindependent float > free float


dindependent float < free float



The technique for establishing and maintaining priorities among the various jobs of any project is known as___________________?


aevent flow scheduling technique


bcritical ratio scheduling


cslotting technique for scheduling


dshort interval scheduling



PERT is___________________?


aan analytic tool in concept


blimit up of event oriented diagrams


cused for research and development projects


dall of the above


View Answer all of the above

A CPM family includes____________________?


aCPA (Critical Path Analysis)


bCPP (Critical Path Plotted)


cMCE (Minimum Cost Expenditure)


dall of the above


View Answer all of the above

PERT analysis is based on____________________?


aoptimistic time


bpessimistic time


cmost likely time


dall of the above


View Answer all of the above

on a PERT/CPM chart represents____________________?


aan ordinary event


ba significant event representing some mile-stone


can event to be transferred to other network chart


ddangling event


View Answer an ordinary event

Criticalpath on PERT/CPM chart is obtained by joining the events having____________________?


amaximum slack


bminimum slack


caverage slack


dno slack


View Answer minimum slack

The assumption in PERT is__________________?


aa project will always be behind schedule, if left uncorrected


bcost of project will always be more than the estimated cost, if no timely corrections are taken


ca project can be subdivided into a set of predictable, independent activities


dactivities are fixed and can’t be changed ,



Goto Page No.

Page 61 of 190

Alphabetical MCQs Categories

Here below You find all kind of categories of MCQs in alphabetical order.


"Comprehensive Collection of MCQs: Alphabetically Organized by Subject"

"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"


BolPakistan

bolpakistan.com.pk includes Job Mcqs and Pak Mcqs is the Top Largest Mcqs Forum in World, in which you can read Mcqs of All Subjects, PPSC test preparation, FPSC, NTS and PPSC PAST PAPERS, PPSC PAST MCQS. A Collection of Repeated MCQs for JOBs seekers.

Copyright © 2024, Designed & Developed by BolPakistan