PERT/CPM, techniques can be used for following applications____________________?


aonce through project

✖


bmaintenance jobs

✖


cresearch and development

✖


dall of the above

✓


View Answer all of the above

CPMis___________________?


asynthesising in concepts

✖


bis built of activities oriented program-mes

✖


cis, based on one time eytimate

✖


dall of the above

✓


View Answer all of the above

Pick up the incorrect statement from the following. A critical ratio scheduling____________________?


aestablishes the relative priorities among various activities on a common basis

✖


bdetermines the status of each activity

✖


cadjusts automatically changes in activity progress

✖


dnone of the above

✓


View Answer none of the above

The time which results in the least possible direct cost of an activity is known as________________?


anormal time

✖


bslow time

✓


ccrash time

✖


dstandard time

✖


View Answer slow time

Critical Path Net Work helps an engineer_________________?


ato concentrate his attention on critical activities

✖


bto divert the resources from non-critical advanced activities to critical activities

✖


cto be cautious for avoiding any delay in the critical activities to avoid delay of the whole project

✖


dall of the above

✓


View Answer all of the above

The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as_________________?


aduration

✖


btotal float

✖


cfree float

✓


dinterfering float

✖


View Answer free float

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to__________________?


alatest start time – earliest start time

✖


blatest finish time – earliest finish time (EFT)

✖


cTL-EFT

✖


dall of the above

✓


View Answer all of the above

The probability distribution of activity times in PERT follows following distribution__________________?


anormal

✖


bbinomial

✖


cbeta

✓


dexponential

✖


View Answer beta

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good______________________?


aEF=ES+D

✖


bLS=LF-D

✖


cLF = LS + D

✖


dall of the above

✓


View Answer all of the above

The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?


aevent

✖


bfree float

✖


cartificial

✖


ddummy

✓


View Answer dummy

Goto Page No.

Page 63 of 190

Alphabetical MCQs Categories
—

Here below You find all kind of categories of MCQs in alphabetical order.


"Comprehensive Collection of MCQs: Alphabetically Organized by Subject"
—

"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"


BolPakistan

bolpakistan.com.pk includes Job Mcqs and Pak Mcqs is the Top Largest Mcqs Forum in World, in which you can read Mcqs of All Subjects, PPSC test preparation, FPSC, NTS and PPSC PAST PAPERS, PPSC PAST MCQS. A Collection of Repeated MCQs for JOBs seekers.

Copyright © 2024, Designed & Developed by BolPakistan