The most reliable estimate is_________________?


aDetailed estimate


bPreliminary estimate


cPlinth area estimate


dCube rate estimate


View Answer Detailed estimate

While preparing a detailed estimate__________________?


a Dimension should be measured correct to 0.01 m


b Area should be measured correct to 0.01 sqm


cVolume should be measured correct to 0.01 cum


d All the above


View Answer All the above

The expected out turn of 2.5 cm cement concrete floor per mansion per day__________________?


a 2.5 sqm


b 5.0 sqm


c7.5 sqm


d10 sqm


View Answer 7.5 sqm

Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds_________________?


a2.0 %


b 2.5 %


c 4.0 %


d 5.0 %


View Answer 5.0 %

The measurement is not made in square metres in case of________________?


a D.P.C. (Damp proof course)


bForm works


c Concrete Jeffries


d R.C. Chhajja


View Answer R.C. Chhajja

The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is_______________?


aRs. 400


bRs. 425


cRs. 450


dRs. 500


View Answer Rs. 450

The trap which is provided to disconnect the house drain from the street sewer is called_________________?


aMaster trap


b Intercepting trap


cInterception manhole


dAll the above


View Answer All the above

Pick up the excavation where measurements are made in square metres for payment ?


aOrdinary cuttings up to 1 m


bSurface dressing up to 15 cm depths


c Surface excavation up to 30 cm depths


d Both B. and C.


View Answer Both B. and C.

In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and_________________?


a Breadth of the wall


b Half breadth of wall on each side


cOne fourth breadth of wall on each side


dNone of these



The area is measured correct to the nearest___________________?


a 0.01 sqm


b0.02 sqm


c0.03 sqm


d 0.04 sqm


View Answer 0.01 sqm

Goto Page No.

Page 96 of 302

Alphabetical MCQs Categories

Here below You find all kind of categories of MCQs in alphabetical order.


"Comprehensive Collection of MCQs: Alphabetically Organized by Subject"

"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"


BolPakistan

bolpakistan.com.pk includes Job Mcqs and Pak Mcqs is the Top Largest Mcqs Forum in World, in which you can read Mcqs of All Subjects, PPSC test preparation, FPSC, NTS and PPSC PAST PAPERS, PPSC PAST MCQS. A Collection of Repeated MCQs for JOBs seekers.

Copyright © 2024, Designed & Developed by BolPakistan