The rate of payment is made for 100 cu m (per % cu m) in case of__________________?


aEarth work in excavation

✖


b Rock cutting

✖


c Excavation in trenches for foundation

✖


dAll the above

✓


View Answer All the above

Brick walls are measured in sq. m if the thickness of the wall is_________________?


a10 cm

✓


b15 cm

✖


c 20 cm

✖


dNone of these

✖


View Answer 10 cm

If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by_______________?


aMid-section formula

✖


bTrapezoidal formula

✖


c Prismoidal formula

✖


dAll the above

✓


View Answer All the above

A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is__________________?


a 500 m3

✖


b1000 m 3

✖


c1500 m3

✓


d2000 m3

✖


View Answer 1500 m3

In the mid-section formula__________________?


aThe mean depth is the average of depths of two consecutive sections

✖


bThe area of mid-sections is calculated by using mean depth

✖


cThe volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections

✖


dAll of the above

✓


View Answer All of the above

The cross -sections for a highway is taken at_________________?


a Right angle to the centre line

✖


b30 metres apart

✖


c Intermediate points having abrupt change in gradient

✖


d All the above

✓


View Answer All the above

According to Indian Standards Institute, the actual size of modular bricks is_______________?


a23 cm × 11.5 cm × 7.5 cm

✖


b25 cm × 13 cm × 7.5 cm

✖


c19 cm × 9 cm × 9 cm

✓


d20 cm × 10 cm × 10 cm

✖


View Answer 19 cm × 9 cm × 9 cm

The assumption on which the trapezoidal formula for volumes is based, is________________?


a The end sections are parallel planes

✖


b The mid-area of a pyramid is half the average area of the ends

✖


cThe volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied

✖


d All the above

✓


View Answer All the above

The brick work is not measured in cu m in case of_______________?


aOne or more than one brick wall

✖


bBrick work in arches

✖


cReinforced brick work

✖


d Half brick wall

✓


View Answer Half brick wall

While estimating the qualities for the construction of a building, the correct metric unit is________________?


aMetre for length

✖


bCubic metre for area

✖


c Square metres for volume

✖


dLitre for capacity

✓


View Answer Litre for capacity

Goto Page No.

Page 98 of 302

Alphabetical MCQs Categories
—

Here below You find all kind of categories of MCQs in alphabetical order.


"Comprehensive Collection of MCQs: Alphabetically Organized by Subject"
—

"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"


BolPakistan

bolpakistan.com.pk includes Job Mcqs and Pak Mcqs is the Top Largest Mcqs Forum in World, in which you can read Mcqs of All Subjects, PPSC test preparation, FPSC, NTS and PPSC PAST PAPERS, PPSC PAST MCQS. A Collection of Repeated MCQs for JOBs seekers.

Copyright © 2024, Designed & Developed by BolPakistan