period in a septic tank is assumed___________________?


a20 minutes


b 25 minutes


c30 minutes


d40 minutes


View Answer 30 minutes

Pick up the incorrect statement regarding a master trap from the following ?


a It is provided in between the lower end of the house drain and the street sewer


bIt is provided a cleaning eye at the top of the trap


cThe mica flap valve which opens inwards only, is fitted at the top of the inlet pipe


dThe water seal is less than that of ordinary traps



The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended___________________?


a100 mm


b150 mm


c 200 mm


d 175 mm


View Answer 150 mm

Pick up the correct statement from the following?


aThe incidental expenses of a miscellaneous character which could not be predicted during preparation of the estimate, is called contingencies


bAdditional supervising staff engaged at work site, is called work charged establishment


c Detailed specifications specify qualities, quantities and the proportions of materials to be used for a particular item


dAll the above


View Answer All the above

The correct Prismoidal formula for volume is________________?


a D [first area + last area + Even area + 2 odd areas]


bD/3 [first area + last area + 4 Even area + 2 odd areas]


c D/3 [first area + last area + 2 Even area + 4 odd areas]


d D/6 [first area + odd areas]



The order of booking dimensions is________________?


aLength, breadth, height


bBreadth, length, height


cHeight, breadth, length


d None of these



The unit of measurement is per quintal for the following?


a Collapsible gates with rails


bRolling shutters


cExpanded metal wire netting


d M.S. reinforcement of R.C.C. works



The ‘centre line method’ is specially adopted for estimating_________________?


a Circular buildings


bHexagonal buildings


cOctagonal buildings


dAll the above


View Answer All the above

The inspection pit or chamber is a manhole provided in a base drainage system________________?


a At every change of direction


bAt every change of gradient


cAt every 30 m intervals


dAll the above


View Answer All the above

In case of laying gullies, siphons, intercepting traps, the cost includes_______________?


a Setting and laying


bBed concreting


cConnection to drains


dAll of these


View Answer All of these

Goto Page No.

Page 94 of 302

Alphabetical MCQs Categories

Here below You find all kind of categories of MCQs in alphabetical order.


"Comprehensive Collection of MCQs: Alphabetically Organized by Subject"

"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"


BolPakistan

bolpakistan.com.pk includes Job Mcqs and Pak Mcqs is the Top Largest Mcqs Forum in World, in which you can read Mcqs of All Subjects, PPSC test preparation, FPSC, NTS and PPSC PAST PAPERS, PPSC PAST MCQS. A Collection of Repeated MCQs for JOBs seekers.

Copyright © 2024, Designed & Developed by BolPakistan