Home / jobmcqs / C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"