Which of the following are parameters involved in computing the total cost of a software development project ?


aHardware and software costs


bEffort costs


cTravel and training costs


dAll of the mentioned


View Answer All of the mentioned

What can be used to complement decomposition techniques and offer a potentially valuable estimation approach in their own right ?


aAutomated estimation tools


bEmpirical estimation models


cDecomposition techniques


dBoth Automated estimation tools and Empirical estimation models



Which of the following is not an option to achieve reliable cost and effort estimate ?


aBase estimates on similar projects that have already been completed


bUse one or more empirical models for software cost and effort estimation


cUse relatively simple decomposition techniques to generate project cost and effort estimates


d The ability to translate the size estimate into human effort, calendar time, and dollars



The project planner examines the statement of scope and extracts all important software functions which is known as___________________?


aAssociation


bDecomposition


cPlanning process


dAll of the mentioned


View Answer Decomposition

Which of the following is not considered as a risk in project management ?


aSpecification delays


bProduct competition


cTesting


dStaff turnover


View Answer Testing

A 66.6% risk is considered as__________________?


avery low


blow


cmoderate


dhigh


View Answer high

Which of the following is/are main parameters that you should use when computing the costs of a software development project ?


atravel and training costs


bhardware and software costs


ceffort costs (the costs of paying software engineers and managers)


dall of the mentioned


View Answer all of the mentioned

Which of the following is an important factor that can affect the accuracy and efficacy of estimates ?


aProject size


bPlanning process


cProject complexity


dDegree of structural uncertainty


View Answer Project size

Quality planning is the process of developing a quality plan for__________________?


ateam


bproject


ccustomers


dproject manager


View Answer project

The process each manager follows during the life of a project is known as ___________________?


aProject Management


b Manager life cycle


cProject Management Life Cycle


dAll of the mentioned



Goto Page No.

Page 155 of 190

Alphabetical MCQs Categories

Here below You find all kind of categories of MCQs in alphabetical order.


"Comprehensive Collection of MCQs: Alphabetically Organized by Subject"

"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"


BolPakistan

bolpakistan.com.pk includes Job Mcqs and Pak Mcqs is the Top Largest Mcqs Forum in World, in which you can read Mcqs of All Subjects, PPSC test preparation, FPSC, NTS and PPSC PAST PAPERS, PPSC PAST MCQS. A Collection of Repeated MCQs for JOBs seekers.

Copyright © 2024, Designed & Developed by BolPakistan