Most common method of prestressing used for factory production is________________?


aLong line method

✓


b Freyssinet system

✖


cMagnel-Blaton system

✖


dLee-Macall system

✖


View Answer Long line method

Prestress loss due to friction occurs________________?


aonly in post-tensioned beams

✓


bonly in pretensioned beams

✖


cin both post-tensioned and preten-sioned beams

✖


dnone of the above

✖



High carbon content in the steel causes_______________?


adecrease in tensile strength but increase in ductility

✖


bincrease in tensile strength but decrease in ductility

✓


cdecrease in both tensile strength and ductility

✖


d increase in both tensile strength and ductility

✖



Ultimate strength of cold drawn high steel wires_______________?


aincreases with increase in diameter of bar

✖


bdecreases with increase in diameter of bar

✓


cdoes not depend on diameter of bar

✖


dnone of the above

✖



Cube strength of controlled concrete to be used for pretensioned and post-tensioned work respectively should not be less than__________________?


a35 MPa and 42 MPa

✖


b42 MPa and 35 MPa

✓


c 42 MPa and 53 MPa

✖


d 53 MPa and 42 MPa

✖


View Answer 42 MPa and 35 MPa

Stress strain curve of high tensile steel_______________?


a has a definite yield point

✖


bdoes not show definite yield point but yield point is defined by 0.1% proof stress

✖


cdoes not show definite yield point but yield point is defined by 0.2% proof stress

✓


ddoes not show definite yield point but yield point is defined by 2% proof stress

✖



Which of the following has high tensile strength ?


aplain hot rolled wires

✖


b cold drawn wires

✓


c heat treated rolled wires

✖


dall have same tensile strength

✖


View Answer cold drawn wires

Which of the following losses of prestress occurs only in pretensioning and not in post-tensioning ?


aelastic shortening of concrete

✓


bshrinkage of concrete

✖


ccreep of concrete

✖


d loss due to friction

✖



Normally prestressing wires are arranged in the_______________?


a upper part of the beam

✖


b lower part of the beam

✓


ccenter

✖


danywhere

✖



In prestressed concrete______________?


aforces of tension and compression change but lever arm remains unchanged

✖


b forces of tension and compressions remain unchanged but lever arm changes with the moment

✓


c both forces of tension and compres-sion as well as lever arm change

✖


dboth forces of tension and compres-sion as well as lever arm remain unchanged

✖



Goto Page No.

Page 253 of 302

Alphabetical MCQs Categories
—

Here below You find all kind of categories of MCQs in alphabetical order.


"Comprehensive Collection of MCQs: Alphabetically Organized by Subject"
—

"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"


BolPakistan

bolpakistan.com.pk includes Job Mcqs and Pak Mcqs is the Top Largest Mcqs Forum in World, in which you can read Mcqs of All Subjects, PPSC test preparation, FPSC, NTS and PPSC PAST PAPERS, PPSC PAST MCQS. A Collection of Repeated MCQs for JOBs seekers.

Copyright © 2024, Designed & Developed by BolPakistan