For a flood control reservoir, the effective storage is equal to_______________?


a useful storage – valley storage


b useful storage + surcharge storage


c useful storage + surcharge storage + valley storage


duseful storage + surcharge storage -valley storag



The total capacity of a reservoir is 25 million cubic metres and dead storage is 5 million cubic metres. If the average volume of sediment deposition is 0.10 million cubic metre per year, then the usefulness of the reservoir will start reducing after_________________?


a 50 years


b150 years


c200 years


d250 year


View Answer 50 years

The uplift pressure on a dam can be controlled by_________________? 0 1) constructing cutoff under upstream face 2) constructing drainage channels bet-ween the dam and its foundation 3) by pressure grouting in foundation The corret answer is?


a only (1)


b both (1) and (2)


cboth (1) and (3)


d(1), (2) and (3)


View Answer (1), (2) and (3)

Horizontal acceleration due to earthquake results in______________?


ahydrodynamic pressure


b inertia force into the body of the dam


cboth (A) and (B)


dnone of the above


View Answer both (A) and (B)

The major resisting force in a gravity dam is___________________?


awater pressure


bwave pressure


cself-weight of dam


d uplift pressure


View Answer self-weight of dam

The maximum permissible eccentricity for no tension at the base of a gravity dam is__________________?


aB/2


bB/3


cB/4


dB/6


View Answer B/6

As compared to gravity dams, earthen dams__________________?


aare costlier


bare less susceptible to failure


crequire sound rock foundations


drequire less skilled labour



Seepage through embankments in an earthen dam is controlled by_______________?


a drainage filters


b relief wells


cdrain trenches


dprovision of downstream berms


View Answer drain trenches

Main purpose of mean water training for rivers is________________?


aflood control


b to provide sufficient depth of water in navigable channels, during low water periods


c to preserve the channel in good shape by efficient disposal of suspended and bed load


d all of the above



The flow of water after spilling over the weir crest in chute spillway and side channel spillway respectively are_________________?


aat right angle and parallel to weir crest


bparallel and at right angle to weir crest


cparallel to weir crest in both


dat right angle to weir crest in both



Goto Page No.

Page 145 of 302

Alphabetical MCQs Categories

Here below You find all kind of categories of MCQs in alphabetical order.


"Comprehensive Collection of MCQs: Alphabetically Organized by Subject"

"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"


BolPakistan

bolpakistan.com.pk includes Job Mcqs and Pak Mcqs is the Top Largest Mcqs Forum in World, in which you can read Mcqs of All Subjects, PPSC test preparation, FPSC, NTS and PPSC PAST PAPERS, PPSC PAST MCQS. A Collection of Repeated MCQs for JOBs seekers.

Copyright © 2024, Designed & Developed by BolPakistan