Total float for any activity is defined as the difference between________________?


a its latest finish time and earliest start time for its successor activity

✖


b its latest start time and earliest start time

✓


c its latest start time and earliest finish time

✖


dits earliest finish time and earliest start time for its successor activity

✖



Free float for any activity is defined as the difference between__________________?


a its earliest finish time and earliest start time for its successor activity

✓


b its latest start time and earliest start time

✖


cits latest finish time and earliest start time for its successor activity

✖


dits earliest finish time and latest start time for its successor activity

✖



The independent float affects only_______________?


apreceding activities

✖


bsucceeding activities

✖


c the particular activity involved

✓


dnone of the above

✖



What estimate would you give for the variance in above problem ?


a81

✓


b54

✖


c36

✖


d 9

✖


View Answer 81

The time with which direct cost does not reduce with the increase in time is known as_________________?


a crash time

✖


bnormal time

✓


coptimistic time

✖


dstandard time

✖


View Answer normal time

The direct cost of a project with respect to normal time is________________?


aminimum

✓


bmaximum

✖


czero

✖


dinfinite

✖


View Answer minimum

Economic saving of time results by crashing_________________?


acheapest critical activity

✓


bcheapest non-critical activity

✖


ccostliest critical activity

✖


dcostliest non-critical activity

✖



Slack time refers to_______________?


aan activity

✖


ban event

✓


cboth event and activity

✖


dnone of the above

✖


View Answer an event

The constraints in case of resource smoothening operation would be_______________?


aresources

✖


bproject duration time

✓


cboth resources and project duration time

✖


d none of the above

✖


View Answer project duration time

Crash project duration is obtained by summing the________________?


anormal durations for all the activities

✖


bcrash durations for all activities

✖


ccrash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

✖


dcrash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

✓



Goto Page No.

Page 123 of 302

Alphabetical MCQs Categories
—

Here below You find all kind of categories of MCQs in alphabetical order.


"Comprehensive Collection of MCQs: Alphabetically Organized by Subject"
—

"Discover an extensive collection of multiple-choice questions (MCQs) neatly categorized by subject from A to Z. This resource is designed for anyone eager to explore various topics in a straightforward and organized manner. Whether you're a student preparing for exams, an educator seeking supplementary materials, or simply curious about different subjects, this compilation offers a convenient way to learn and assess your knowledge. With questions arranged alphabetically, navigation is effortless, allowing you to delve into subjects of interest at your own pace. Engage, learn, and expand your understanding with this accessible and comprehensive repository of MCQs!"


BolPakistan

bolpakistan.com.pk includes Job Mcqs and Pak Mcqs is the Top Largest Mcqs Forum in World, in which you can read Mcqs of All Subjects, PPSC test preparation, FPSC, NTS and PPSC PAST PAPERS, PPSC PAST MCQS. A Collection of Repeated MCQs for JOBs seekers.

Copyright © 2024, Designed & Developed by BolPakistan